From launch to handover.
Almost every home here was sold before it was built, so the question I am asked most is when. Here is each neighbourhood from its launch to its completion, as the records give it, and where they are silent or disagree, I say so.
ElanCompleted
HarmonyCompleted
1 1 No completion date is on record for Harmony 2 or Harmony 3.
AuraCompleted
AlayaCompleted
Aura GardensCompleted
Recorded as completed, with no launch or completion date on record.
Elysian MansionsRecords disagree
1 1 2 3 88% built at the inspection of .1 The three records disagree with each other, and the same record that marks it completed puts construction at 88%.
Alaya BeachBeing built
Alaya GardensBeing built
Lanai IslandsBeing built
AmaraBeing built
Plagette32Being built
Bo MondeBeing built
Serenity MansionsBeing built
- 1. Source: Property Finder, each neighbourhood’s project record, Majid Al Futtaim developer listing. Checked 28 September 2026.Return
- 2. Source: Bayut, each neighbourhood’s area guide. Checked 28 September 2026.Return
- 3. Source: Majid Al Futtaim, Press release, Majid Al Futtaim breaks ground across two key projects at Tilal Al Ghaf, 22 January 2024. Checked 28 September 2026.Return
Dates as each source gives them on the day checked.
A completion date is the developer's target, not a promise, and a handover follows it by weeks or months. Read the line for the order things happen in, then ask for the date in the contract of the home you are buying.
Figures are drawn from the named third-party and public sources shown, as of the dates shown, and may change. Nothing on this site is financial or investment advice or a guarantee of future value, price or rental return.