Off plan or resale: which makes more sense here?

The answer

Resale if you want to live in Tilal Al Ghaf this year, because only Elan, Aura, Aura Gardens and the first phases of Harmony are built. Off plan if you want a lagoon address, a mansion, or a payment plan running to handover, because every one of those is still under construction and sold out from the developer, so you buy an existing contract. There is no third option: with Bo Monde the only neighbourhood still selling direct, off plan here almost always means a resale of a contract.

Justin Hall, Property Consultant, BlackBrick Property

Last updated

In detail.

The question sounds like a choice of strategy. In Tilal Al Ghaf it is mostly a choice of neighbourhood, because the neighbourhood decides which one you get. Four neighbourhoods are finished and lived in: Elan, Aura, Aura Gardens and the early phases of Harmony. Everything on the water and every mansion neighbourhood is still being built. Majid Al Futtaim has sold out every release except Bo Monde, so “off plan” here nearly always means buying another owner’s contract with the developer, and paying them what they have paid in plus a premium, rather than buying from a sales centre.

A finished home has three things going for it. You can walk it, and I can show you the snagging and the sun path rather than a render. You can live in it or let it from the day of transfer. And the price is the price: you pay it, plus the transfer costs, and it is yours. What you give up is choice of plot and finish, and the long payment plan.

A contract has the payment plan, the plot choice that is left, and in the mansion neighbourhoods the chance to specify the house before it is built. What you take on is the wait, which runs from a few months in Amara and Plagette32 to the end of 2027 in Serenity Mansions and Bo Monde, and the fact that the home you are buying does not exist yet. The developer said in June 2026 that construction is on schedule, and I take that at face value, but I still price every contract on the assumption that the handover date is the earliest you will get the keys, not the latest.

My rule of thumb: buy resale if you need the home within a year or if you need to see it to believe it, and buy a contract if the address you want is only available that way and the payment plan suits your cash. Nothing in either route is a promise about value, and I will not make one.

The figures.

Behind the answer
Built and lived in
Elan, delivered from Q4 2023; Aura, delivered Q3 2024; Harmony 1, complete since June 2024. Each sold out from the developer, so homes change hands on the resale market
Under construction
Alaya, Alaya Beach, Elysian Mansions and Lanai Islands due through 2026; Amara and Plagette32 expected December 2026; Serenity Mansions and Bo Monde expected December 2027. All sold out from the developer except Bo Monde
A typical developer payment plan
Amara and Plagette32 were sold on 10% at booking, 50% during construction and 40% at handover; Elan, Aura, Harmony and Alaya on 10% at booking, 45% during construction, 5% at handover and 40% after handover
The developer on its schedule
On 12 June 2026 Majid Al Futtaim said construction across Tilal Al Ghaf continues in line with the project schedule and the terms of the sale and purchase agreements